Featured Projects

SRG Global is a leader in automotive coating products that needed a new paint fume exhaust system. C-logic was contracted to:
  • Complete scanning for topographical elevations and clearance issues
  • Civil and structural engineering for a 200’ x 60’ platform and more than 150’ of trestles that extended back of over the existing plant to support 8’ diameter duct work
  • Excavated and installed all footers and piers
  • Fabricated and installed all steel including columns, beams, cross bracing, grating, handrail, trestles, Pipe supports, interior supports. This included a running (2) cranes at all times.
  • Demolition of three rooftop structures that housed decommissioned equipment
  • Project management over entire duration of this project
  • All the work was completed on straight time except the switch over from the old Rash units to the new during a 2 week shutdown. This required close coordination with the plant to not interfere with production.The project was completed ahead of schedule and under budget with no issues.

Sun Chemical specializes in high purity oxides and is based out of northern Indiana.

C-logic, Inc. assisted and performed many tasks for them. Our scope of work consisted of:

1. 3-D Scanning
      a. For sperry filters and carbon filter pods
2. Engineering and Design
      a. Included stamped drawings
      b. Included full 3-D renderings of what was designed
3. Fabrication and Paint
      a. Fabricated all platforms, stairs, handrail, ladders, columns, and grating
      b. All steel was cleaned, sandblasted, and painted to customer specifications
4. Transportation and Hauling
      a. Moved all steel, equipment, personnel, and tooling from Lexington, KY to Valparaiso, IN.
5. Demolition
      a. Removed decommissioned equipment and disposed of for customer
      b. Removed pre-existing platforms, handrails, tanks, stairs and ladders, and all relevant material that would have impeded the new structures being installed
      c. Disposed off all steel and material though local recycling companies
6. Installation
      a. C-logic provided all needed hardware, steel, and equipment to complete the job
      b. Installed new fabricated platforms, ladders and stairs, handrailing, columns, and grating.
      c. Grouted all columns to customer specifications
      d. Installed new sperry filters and carbon filter pods using C-logic crane operators, riggers, and certified equipment operators
      e. Installed custom stainless steel chutes under the sperry filters
      f. Finished with touch up painting, final clean up and demobilization of the area, and a walk through with the customer to ensure their satisfaction