SRG_Global

C-logic was contracted to:

  • Complete scanning for topographical elevations and clearance issues
  • Civil and structural engineering for a 200’ x 60’ platform and more than 150’ of trestles that extended back of over the existing plant to support 8’ diameter duct work
  • Excavated and installed all footers and piers
  • Fabricated and installed all steel including columns, beams, cross bracing, grating, handrail, trestles, Pipe supports, interior supports. This included a running (2) cranes at all times.
  • Demolition of three rooftop structures that housed decommissioned equipment
  • Project management over entire duration of this project
  • All the work was completed on straight time except the switch over from the old Rash units to the new during a 2 week shutdown. This required close coordination with the plant to not interfere with production.The project was completed ahead of schedule and under budget with no issues.